Dongshan Marine Station Project Progress

Project Progress as of December 30, 2015
Updated on£º2016-1-10      Visits£º1166

Construction of the main building has been conducted since October 2014. Now, the construction of the two-story basements has finished in July 30 2015.

The application for the certificate of land for the first phase (~4.6 acres) has been permitted since November 2015.

The Dongshan government agreed to transfer the area of about 7 acre near the phase ¢ñ as the phase ¢ò construction land in December 2015.

 

     

The construction site of Dongshan marine station (July 30,2015) 

The land area of Dongshan marine station for the first & second phase